Crish said ODOT in not bound by Hess’
rule. “We go by temperature, not the date,” the
ODOT engineer said. “All we need is two hours of 50-degree
weather.”
The temporary runaround opened in July to carry
traffic around the construction site will be removed over the
winter, Crish said. The large concrete culverts used to span
the Meander Creek will be removed for use in a future ODOT project.
The temporary runaround was not in ODOT’s
original plans for the project. Merchants were outraged when
they learned the state planned to detour traffic several miles
around downtown Niles for several months, and protested to ODOT
officials and state legislators.
After two public meetings at the McKinley Memorial,
ODOT added the temporary runaround and its nearly $300,000 price
tag to the project. Thanks to the temporary span, traffic has
not been disrupted by the bridge replacement project. About
15,000 vehicles use the bridge each day, many of them trucks.
After the temporary runaround is removed, workers
will clean up the site, including planting grass. The seeding
will not be finished until next June, according to Crish.
The construction site is near the intersection
of South Main Street and McKees Lane, about a half mile south
of the Viaduct over the Mahoning River.